2010 2010 2009 2009 2008 2008 2007 2007 2006 2006 2005 2005 2004 2004 2003 2003 2002 2002 2001 2001 2000 2000 1999 1999 1997 1997
Show only main decisions in force Show all
The greyed main decisions have expired.
| 12.28.2001 |
|
Urgent provisions concerning electricity import from France and Switzerland
The Authority for Electricity and Gas has conformed the procedures for the allocation of import capacity to the resolution of the Regional Administrative Court of Lombardia of 28/12/01, which has partially admitted the claims of Swiss electricity companies. The precautionary suspension concerns the allocation of 440 MW of interconnection capacity on the French-Swiss border that initially was exclusively assigned to Italian customers. Waiting for the definitive sentence, the Authority has decided to allocate on that border (through the pro-quota mechanism) a capacity reduced by 220 MW (proportional reduction of applications). |
n.
327/01
|
| 12.27.2001 |
|
Italgas fined 2,582 million euros for insufficient information and errors in billing
The Authority for Electricity and Gas has imposed a fine of 2,582 thousand euro (5 billion lire) on Italgas for omitting to indicate in round-up bills the dates of the last two readings to which the round-up consumption refers. The omission of the date prevents consumers from checking the sums demanded as round-ups. The distributor should also indicate the actual consumption to allow consumers to plan their gas consumption and to check on the frequency of the readings that distributors are required to carry out. Italgas will have to recalculate erroneous round ups because it has in general applied the tariffs in force at the time of the last bill issued instead of taking consumption and tariffs for the period between two meter readings. This meant that users were losing out on any savings they would have been entitled to in cases where the tariffs in force in previous bi-monthly periods were lower than those applied in the last bill issued. |
n.
323/01
|
| 12.27.2001 |
|
Adoption of provisions concerning tariff options related to electricity transportation service and purchase and selling service to captive market for 2002
In resolution n.322/01 the Authority publishes the results of the check on basic, special and additional tariff options for the electricity transportation service presented by operators for captive customers for 2002 (174 operators have presented to the Authority basic tariff options). resolution 322/01 also introduces a tariff regime that should be offered by operators for the period from 01/01/02 to 31/12/02 in cases where they have not presented basic tariff options (16 cases) or basic tariff options have been rejected (3 cases). All special and additional tariff options have been accepted. |
n.
322/01
|
| 12.27.2001 |
|
Delay of the deadline for the yearly interconnection capacity assignment, pursuant to article 2 (7) of the Authority for Electricity and Gas's resolution n.305/01 dated 17 December 2001, and directive to TSO (GRTN) for the reformulat
Due to the appeal against the Authority for Electricity and Gas's resolution n. 305/01 done by Switzerland operators, the resolution entrusts TSO (GRTN) to delay the deadline for the allocation of interconnection capacity for non interruptible customers and for the CIP 6 auctions. |
n.
321/01
|
| 12.27.2001 |
|
Bimonthly adjustment for January-February 2002 of electric tariff components and parameters
As envisaged by the Unified Code on electricity transport and sale tariffs (Authority for Electricity and Gas's resolution n.228/01), the Authority publishes the bimonthly adjustment of electric tariff components and parameters (PG, PGT, CCA) due to variation in the Ct parameter (variable unit allowed cost of electricity produced by thermoelectric plants using commercial fossil fuels). The Ct parameter for the two months January-February 2002 is equal to 3,720 Euro cents/kWh. The PG parameter is set at 5,777 Euro cents/kWh. |
n.
319/01
|
| 12.27.2001 |
|
Definition of wholesale electricity prices for captive market customers for 2002
Resolution n.318/01 sets interim wholesale prices for 2002 for the electricity to captive market to be applied until the bidding system is launched. In particular, the wholesale price component covering fixed generating costs, which is differentiated into time bands (see Authority for Electricity and Gas resolution n.205/99), is determined according to the allowed production costs for thermoelectric plants and reference production levels. |
n.
318/01
|
| 12.27.2001 |
|
Provisional rules for the supply of the electricity despatch service and directive on withdrawal from supply contracts to customers of captive market
Resolution 317/01 defines the tariffs paid by producers and consumers which do not supply reserve services to TSO (GRTN) in order to balance the system. The resolution introduces the exchange contracts: these contracts has to be signed by each part of a bilateral contract with the TSO (GRTN) for the assessment of the settlement between inflows and withdrawals of electricity from the network. Furthermore the resolution establishes that captive customers may withdraw from their annual supply contract without any penalties until 1/1/02 if the contract includes a point of the grid which requires interconnection or CIP 6 capacity. |
n.
317/01
|
| 12.27.2001 |
|
Electric tariffs for domestic users for 2002
In order to guarantee continuity in the tariff regime for domestic users, resolution n.316/01 partially amends Authority for Electricity and Gas resolutions n.163/01 and n.228/01 by setting new transitional values for f parameters and tariff components relative to tariffs D2 and D3. |
n.
316/01
|
| 12.21.2001 |
|
Definition of competitive procedures for 2002 for the transfer by the TSO (GRTN) of the electricity pursuant to article 3 (12) of the legislative decree 79/99.
The Authority sets out the conditions for the competitive procedures through which the TSO (GRTN) must sell the produced electricity by renewable and assimilated sources under the terms of CIP provision n.6/92 (see Minister of Productive Activities' decree of 21/11/00 as modified by decree of 10/12/01). The Authority defines the mechanism allocating the productive capacity on an annual basis, whereas monthly based auctions are abolished in 2002. The resolution defines three different auctions regarding eligible customers willing to unplanned outages, planned outages and others, and minimum bid prices are published. Bands are allocated following a decreasing bidding price order. resolution 308/01 also sets antitrust ceilings on productive capacity such that no operator may apply for more than 20% of bands in each auction and for more than 15% of bands over all auctions. |
n.
308/01
|
| 12.17.2001 |
|
Amendment of Resolutions n.175/00 and n.151/01
Resolution 307/01 amends resolutions n.175/01and n.151/01 by including in the list of subjects fulfilling provision of article 15 (2) of the legislative decree n.79/99 also the "Lucchini S.p.A.". |
n.
307/01
|
| 12.17.2001 |
|
Approval of the regulation concerning the organisation and the rules of the allocation mechanism for the interconnection capacity to be assigned for the year 2002
The resolution approves the rules set out by TSO (GRTN) regarding the allocation mechanisms for interconnection capacity and the amounts of interconnection to be allocated both to interruptible and not interruptible customers. This regulation has to be reported to French Authority, Commission de rigulation de l'ilectriciti (CRE), due to the agreement approved with resolution n.301/01. |
n.
305/01
|
| 12.13.2001 |
|
Approval of the FI parameters pursuant to article 16 (7) of the standard agreement between National Transmission System Operator and owners of power plants included in the national transmission network
According to the standard agreement, pursuant to article 3 (8) of the legislative decree 79/99, adopted with ministerial decree of 22.12.00, the Authority sets the parameters for the calculation of the annual fee covering management and maintenance activities, paid by the TSO (GRTN) to owners of power plants included in the national transmission network. |
n.
304/01
|
| 12.05.2001 |
|
Procedures and conditions for electricity imports for 2002 in the case of insufficient available transportation capacity, pursuant to article 10 (2) of the legislative decree n.79/99, and approval of the agreement between the Authority for Electricity and Gas and Commission de Regulation de l'electriciti on transport capacity allocation over the grid interconnecting Italy and France
Following the directions of the Ministry of Productive Activities the resolution defines the allocation of the interconnection capacities among Italy and neighbouring countries. The total capacity is divided among long terms contracts (2600 MW), capacity reserved to Switzerland, Austrian and Slovenian authorities (1300 MW), capacity reserved to interruptible eligible customers for the next three years (600 MW) and capacity reserved yearly to other eligible customers (1353 MW). In case of capacity scarcity, a pro-rata mechanism is applied to the requests. No company or group of companies can hold capacity rights above 10% on each frontier (North West and North East Pools). TSO (GRTN) has the power to organise a market for the secondary allocation of the capacities obtained by customers. By approving the agreement with CRE the resolution gives to TSO (GRTN) the right to manage the joint allocation of the total interconnection capacity with France, creating the first transnational market for the interconnections in Europe. |
n.
301/01
|
| 11.29.2001 |
|
Postponement of the due date for the conclusion of the procedure determining the distribution service continuity levels in 2000 and for the recognition of costs related to the maintenance of service continuity levels in 2001 |
n.
294/01
|
| 11.29.2001 |
|
Amendment of resolutions n.175/00 and n.151/01
Resolution n.293/01 amends resolutions n.175/01and n.151/01 by including in the list of subjects fulfilling provision of article 15 (2) of the legislative decree n.79/99 also "AEM Torino S.p.A.". |
n.
293/01
|
| 10.30.2001 |
|
Determination, with reference to Eurogen S.p.A.'s plants, of the allowed revenue (RR) for fixed costs covering and of the conventional productivity for 2000-2001, in order to calculate non-recoverable costs, pursuant to article 5 (3) an
The Authority defines the value of the RR (allowed revenue) parameters for 2000-2001 and the conventional productivity of Eurogen S.p.A. in order to determine its allowed stranded costs. |
n.
244/01
|
| 10.18.2001 |
|
Amendment of resolutions n.175/00 and n.151/01
Resolution n.230/01 amends resolutions n.175/01and n.151/01 by including in the list of subjects fulfilling provision of article 15 (2) of the legislative decree 79/99 also the "ASM Rovereto". |
n.
230/01
|
| 10.18.2001 |
|
Contractual conditions for the natural gas supply
The Authority for Electricity and Gas has set minimum standards for the contracts signed among gas consumers and gas suppliers. The new standards will cover the captive market, 15 million consumers whose contracts were previously drawn up unilaterally by the gas suppliers. The resolution focuses on deposits, frequency of meter reading, and the interest rates charged on late payments. The new conditions must be inserted in new contracts and will also applied retroactively to all existing contracts. |
n.
229/01
|
| 10.18.2001 |
|
Unified Code of The Authority for Electricity and Gas's provisions for the supply of electricity transport, metering and sale services
The Authority for Electricity and Gas sets out the new tariff regime for the transport and sale of electricity. The reform abrogates wheeling tariffs envisaged by resolution 13/99 and extends to all final customers the rules on transport tariffs for captive market set by resolution 204/99. In order to do this the resolution partially amends and reforms resolutions 204/99 and 205/99. The main elements of the reform are: 1)the reduction of user categories from 9 to 6; 2)the separation of tariff options for transport and tariff options for sale. The resolution keeps the structure of constraints introduced by resolution 204/99 for transport tariffs only and sets a new tariff (CCA) for sale services. As in resolution 204/99, for domestic customers a system providing greater protection is envisaged. |
n.
228/01
|
| 09.07.2001 |
|
Gas transportation tariffs approved
Eni's and Edison's transportation tariffs are approved by the Authority for Electricity and Gas. |
n.
193/01
|
| 08.07.2001 |
|
Introduction of the right of withdrawal from annual and multi-annual contracts
The guidelines gives large gas consumers (eligible customers) the right to withdraw from their existing contracts and change supplier. The guidelines concern both the sale and delivery of gas and require suppliers to grant their customers the right to withdraw from existing or future contracts giving advance notice of: 1) six months in case of multi-annual contracts, 2) three months in case of annual contracts. |
n.
184/01
|
| 08.07.2001 |
|
Postponement of the due date for determining the distribution service continuity levels for 2000 pursuant to article 8 of resolution n.202/99 |
n.
183/01
|
| 08.01.2001 |
|
Definition of criteria for the assessment of technical checks' results and determination of the estimated value pursuant to article 5 of the resolution n.202/99
Resolution n.178/01, having regard to Authority for Electricity and Gas's resolution n.202/99, defines three index for the assessment of results of the technical checks based on service continuity data. |
n.
178/01
|
| 08.01.2001 |
|
Definition of basic actual levels and performance improvement levels of service continuity for each year in the period 2000-2003 for territorial areas of distributors envisaged by article 2 (1b), (2), (4) of resolution n.202/99 |
n.
177/01
|
| 07.25.2001 |
|
Determination of the parameter PG for 2000 and integration to resolution n.204/99
The parameter PG, which is the unit component of tariff option TV1 intended to cover unit electricity purchase costs for captive market and which depends on the average actual wholesale price for captive market, is set for 2000 at 49,6 #/kWh. |
n.
174/01
|
| 07.19.2001 |
|
Adjustment of tariff options and tariffs for electricity distribution and sale services to captive market for 2002 and provisions about the Cassa Conguaglio per il settore eletrico (Compensation Fund)
In accordance with resolution n.204/99, the Authority for Electricity and Gas adjusts with the price cap method the parameters of tariff option TV1 and those of the single tariff for domestic users D1 for 2002. In addition, the Authority for Electricity and Gas makes the required adjustments in order to bring tariffs D2 and D3 gradually into line with tariff D1 by the end of 2002. Resolution 163/01, in order to consider the costs sustained by distributors for electricity service continuity improvement, envisages also an increase in the allowed costs for the adjustment of components related to the distribution service. |
n.
163/01
|
| 07.11.2001 |
Procedures for the presentation and criteria for the check of Cesi S.p.A.'s research projects, which are financed by the Fund envisaged by article 11 (1) of the decree of the Ministry of Productive Activities 26/01/00
On the basis of Authority for Electricity and Gas resolution 220/00, for 2000 and until the research projects' selection envisaged by decree 26/01/00 starts working (but not later than 31/12/01), the resources of the Research Activities Fund (within the Compensation Fund) are allocated to the CESI S.p.A. resolution 158/01 sets out the conditions for the presentation and the criteria for the check by the TSO (GRTN) of the CESI's research projects. |
n.
158/01
|
|
| 07.05.2001 |
|
Statement of subjects not fulfilling provision of article 15 (2) of the legislative decree n.79/99
The Authority publishes the list of subjects that have not fulfilled the authorisation procedure for the building of new plants from renewable sources (article 15 (2) of the legislative decree 79/99). |
n.
151/01
|
| 06.26.2001 |
|
Statement of subjects fulfilling provision of article 15 (2) of the legislative decree n.79/99
The resolution states the fulfilment of the authorisation procedure for the building of new plants from renewable sources (article 15 (2) of the legislative decree 79/99) to 70 more subjects that have presented explanations in accordance with resolution 175/00. |
n.
144/01
|
| 06.21.2001 |
|
Directive concerning the conversion into Euro of tariff unit fees and the consumption billing
Resolution 136/01 regulates the conversion into Euro of tariff unit fees and the consumption billing in Euro by distribution companies (optional from 01/07/01, compulsory from 01/03/02). |
n.
136/01
|
| 06.21.2001 |
|
Modification and integration of the resolution document 52/99
Integration of the Authority for Electricity and Gas resolution on the distribution tariffs indexing to the raw materials cost. The resolution states that the supply tariff must be up-dated according to a new formula given in the document, if the annual index variation is bigger than 5%. |
n.
135/01
|
| 06.21.2001 |
|
Integration of the Resolution 237/00, distribution tariffs reform
Integration of the Authority for Electricity and Gas resolution on the supply activity to the captive market. |
n.
134/01
|
| 06.05.2001 |
|
Postponement of the date on which the provisions envisaged by the directive for the accounting and administrative unbundling of the electricity companies and related publication and communication obligations, pursuant to article 15 (2) of the resolution n.61/99, will come into force |
n.
122/01
|
| 05.30.2001 |
|
Criteria to define gas transportation tariffs
Criteria to calculate the transportation and despatch prices on the national and regional gas network. The tariff on the national network is based on "entry/exit" prices for the booked capacity at the point of entry to pipelines and at the interconnection points with the regional networks, and on a fee for booked capacity on the regional network. The decree contains also a six-year programme of tariff incentives for new infrastructure investments; the return on the net invested capital is fixed at 7.95%. The same calculation method is set for LNG regassification plants (with a return on the capital invested of 9.15%). The price cap will stay into force for 4 years and will be adjusted annually. |
n.
120/01
|
| 05.25.2001 |
|
Determination, having regard to article 5 (3) and (8) of the ministerial decree 26/01/00 towards Elettrogen S.p.A.
The Authority defines the value of the RR (allowed revenue) parameters for 2000, the adjustments to be applied over the next 6 years and the conventional productivity for each of the Elettrogen plants, in order to determine its allowed stranded costs. |
n.
115/01
|
| 05.25.2001 |
|
Definition of the electricity wholesale price, the allowed variable unit costs, and the procedure for the updating of RR (allowed revenues) parameters in order to calculate non-recoverable costs
The Authority for Electricity and Gas defines the electricity wholesale price for 2000-2001, the allowed variable unit cost of production for 2000-2001 and the procedure for updating the RR (allowed revenue) from 2001 on, in order to determine the stranded costs pursuant to ministerial decrees of 26/01/00 and 17/04/01. In particular, the annual adjustment of allowed revenue will take into account the consumer price index, a productivity increase of 4% per year in nominal terms and changes in fixed costs due to investments related to contractual commitments undertaken prior to 19/02/97. Allowed revenue will be reduced by an appropriate amount in cases where the plant has other sources of revenue in addition to the sale of electricity (e.g. the provision of reserve services for the network operator). |
n.
114/01
|
| 05.17.2001 |
|
Modification of resolution n. 204/99 |
n.
110/01
|
| 05.03.2001 |
|
Fixing on account for 2001 of the fee envisaged by article 5 (4) of the resolution n.162/99
Resolution 101/01 sets the international wheeling fee on electricity imports, envisaged by Authority for Electricity and Gas Resolution 162/99, due to the TSO (GRTN) for 2001: since costs estimation is not yet available, the fee is set as in 2000 (0,6 #/kWh, see Resolution 180/99). |
n.
101/01
|
| 04.30.2001 |
|
Provisions concerning the electricity market pursuant to article 5 of the legislative decree n.79/99
Resolution 96/01 defines a set of general principles which the organisation, management and functioning of the electricity market must comply with. The Authority intends to prevent the exercise of market power by means of transparent procedures, non-discriminatory conditions for operators and efficient price-setting mechanisms. Moreover, to enable the Authority to monitor the behaviour of the operators in the power exchange, the provision also lists the information data sets the market operator will be required to meet. |
n.
96/01
|
| 04.30.2001 |
|
Conditions for the supply of the public electricity despatching service throughout the country pursuant to article 3 (3) of the legislative decree n.79/99
The Authority sets out the conditions for the supply of the electricity despatching service throughout the country with due regard for the safety and security of the national electricity system. Special reference is given to the arrangements for handling congestion (insufficient network transportation capacity), maintaining the balance between demand and supply and the management of reserved capacity. On the basis of these conditions, the TSO (GRTN) will draw up the rules for despatch that it carries out under license. These rules will apply to all network users. |
n.
95/01
|
| 03.22.2001 |
|
Urgent proposal to the Minister of Productive Activities about the definition of the general system costs pursuant to article 3 (11) of the legislative decree n.79/99
In order to clarify and simplify the procedure for the recognition of stranded costs and to give customers a more reliable idea of the entailed amounts, the Authority asks the Minister of Productive Activities to clarify how decree of 26/01/00 should be applied in cases of change of ownership and asks also that, independently of the method used to calculate stranded costs, the burden on consumers should not be higher than it would have been if plants had not been sold. |
n.
67/01
|
| 03.22.2001 |
|
Modification of the verification procedures on eligible customers status having regard to resolution n. 91/99
With resolution 66/01, which amends resolution n.91/99, the Authority simplifies the procedures for the annual confirmation of eligible customers status by shifting the onus of submitting the annual data on the electricity withdrawals of eligible customers connected to the network directly to distributors: eligible customers are no longer required to submit any notification. A self-certification exists only for eligible customers who self-produce part of the electricity they use. |
n.
66/01
|
| 03.22.2001 |
|
Urgent provisions concerning electricity wheeling contracts and amendments to resolutions n.13/99 and n.119/00
With resolution 63/01 the Authority takes steps to amend the procedure envisaged by article 4 (4) of resolution 13/99 regarding the supply of the wheeling service, partly to allow operators to use the interconnection capacity allocated for the period from 01/04/01 to 31/12/01 as soon as the capacity actually becomes available (see resolution n.21/01). As a result, prior authorisation is no longer needed to draw up wheeling contracts in derogation: such contracts may be stipulated directly and then submitted to the Authority for approval. |
n.
63/01
|
| 03.22.2001 |
|
Integration to provisions regarding two-monthly contributions to production-distribution companies pursuant to article 6 (11) of the resolution n.70/97 |
n.
62/01
|
| 03.13.2001 |
|
Urgent provisions concerning technical rules for the measurement of electricity pursuant to article 13 (4) of the resolution n.138/00
Resolution 59/01, amending resolution n.138/00, extends the deadline for the submission by the TSO (GRTN) to the Authority of the "technical rules for the electricity measurement" and for the adoption by the Authority of these rules. |
n.
59/01
|
| 03.13.2001 |
|
Definition of the compensation fund in the distribution tariffs
The document gives further explanations of the calculation method of the annual average distribution cost and of the compensation fund. |
n.
58/01
|
| 02.28.2001 |
|
Adoption of the technical rules published by the National Transmission System Operator (GRTN) pursuant to article 3 (6) of the legislative decree n.79/99
With resolution n.39/99, the Authority for Electricity and Gas approves, with some amendments, the TSO's "technical connection rules", pursuant to article 3 (6) of the legislative decree n.79/99, published on the basis of the guidelines issued by the Authority in resolution 52/00. The definitive version is published by the TSO on 1st March 2001. |
n.
39/01
|
| 02.14.2001 |
|
Determination of the contributions envisaged by CIP provision n. 34/90
Resolution n.24/01 closes the proceeding started with resolution n.183/99, and extended with resolution n.91/00 and n.195/00, for the determination of contributions due to production-distribution companies following CIP provision n.34/90 (cogeneration and hydroelectric plants). |
n.
24/01
|
| 02.14.2001 |
|
Amendments and integrations to resolution n.243/00
In resolution n.22/01, by amending resolution n.243/00, the Authority for Electricity and Gas publishes definitive results of the check on basic, special and additional tariff options presented by operators for the captive customers for 2001 (21 basic tariff options not presented; 10 basic tariff options rejected; 1 additional tariff option rejected). |
n.
22/01
|
| 02.14.2001 |
|
Definition of procedures and conditions for electricity imports for 2001 when further transportation capacity becomes available following unplanned outages and amendments to resolution n.219/00
Resolution n.21/01 defines procedures and conditions for the allocation of further transportation capacity at the borders, with respect to the capacity envisaged by Authority for Electricity and Gas's resolution n.219/00, that becomes available as a consequence of users' willingness to unplanned outages (TSO estimate: 200MW). The pro-quota mechanism is amended to avoid an excessive sharing out of this additional capacity and the TSO is responsible for the definition of the allocation procedure. |
n.
21/01
|
| 02.14.2001 |
|
Adoption of provisions concerning the management of the "new plants from renewable and assimilated sources account"
Resolution n.20/01 concerns the electricity produced by renewable and assimilated sources under the terms of CIP provision n.6/92, purchased and sold by the TSO (GRTN) (see Ministry of Productive Activities' decree of 21/11/00) and the procedures for the management of the "new plants from renewable and assimilated sources account" funded by the A3 tariff component's revenue. |
n.
20/01
|
| 01.24.2001 |
|
Modification of the resolution n. 236/00
Change of the article concerning intervention after the delivery point. The obligation to register the time the intervention takes is abolished and on the other hand it is introduced the right to stop the supply in case of gas dispersion. |
n.
5/01
|